6.3.3 Constructing
Bypass Duct







FIGURE 13 - Bypass Duct
Bypass CFM
"A" Pressure Drop through the Furnace
Width 0.10 0.15 0.20 0.25 0.30 0.35 0.40 0.45 0.50
3"
490 530 610 700 780 830 900 960 1010
4"
630 750 870 980 1090 1160 1250 1310 1400
5"
850 1010 1190 1300 1410 1520 1640 1730 1810
6"
1050 1290 1480 1650 1800 1940 2090 2200 2320
7"
1250 1510 1760 1960 2180 2320 2500 2650 2800
8"
1490 1810 2100 2350 2560 2760 2940 3110 3290
9"
1700 2100 2400 2700 2970 3200 3400 3600 3800
10"
1920 2350 2760 3090 3650 4020 4300 4550 4800
When the CFM of air throughput is greater than desirable or permissible for the unit,
a bypass duct may be constructed. Follow these instructions to determine the correct
size of the bypass duct.
Directions for Sizing
Bypass Duct
6.3.2 Duct Furnace
Blower Connections
Proper arrangements of blower and duct furnace with respect to angle of approach
of the duct connection and the arrangement of the discharge opening of the blower
are shown. Blowers should be bottom horizontal discharge when coupled to the duct
furnace. When a top horizontal discharge blower is connected to the duct furnace, be
sure that sufcient length of duct is provided to permit even ow of air at the end of the
duct. Or, bafes may be inserted between the blower and the heater to assure an even
ow of air across the heat exchanger. See illustrations in FIGURE 12 A, B, and C.
FIGURE 12A - Straight
through Air Blower
Connection



















































WARNING
The furnace must be installed on the positive pressure side of the air-circulating blower. See Hazard
Levels, page 2.
FIGURE 12B - Blower
Connection With
Elbows Up or Down
FIGURE 12C - Blower
Connection with Elbows
Right or Left
1) From the tables in Paragraph 6.3.1, nd the pressure drop (P.D.) and the allowable
CFM for the furnace that is being installed.
Example: Standard Size 170 @ 70°F temperature rise; P.D. .33; CFM 1790