Compressor Oil Charge (POE Oil)
Compressor Model cc oz
ZP24K5E 621 21
ZP36K5E 1124 38
ZP54KCE 1242 42
ZP57K3E 1715 58
ZP61KCE 1538 52
ZPD61KCE 1774 60
ZP72KCE 1774 60
ZP83KCE 1656 56
ZPD83KCE 1656 56
ZP137KCE 3253 110
ZPD137KCE 3135 106
ZPT144KCE 3312 112
ZP154KCE 3253 110
ZPDT14MCE 3135 106
Important NOTES: These R-410A
compressors use a polyolester (POE)
lubricant. Types of recommended POE
oil are Copeland Ultra 22 CC, Copeland Ultra
32 CC, Copeland Ultra 32-3MAF, Mobil EAL,
Arctic 22 CC, Uniqema Emkarate RL32CF, or
Uniqema RL32-3MAF.
POE oil absorbs moisture much quicker
and to a greater degree than standard
mineral oil. The compressor must not
be left open longer than 15 minutes
during replacement. During installation
the system must be swept with an
inert gas such as dry nitrogen to keep
moisture from entering the compressor
and prevent the formation of oxides.
4, follow procedures indicated for burnout cleanup.
Dispose of oil and compressor using an approved environmentally safe
disposal method.
• Step 3. Mount the Replacement Compressor
Do not remove the dust cover or rubber shipping plugs until all other system
connections are complete (i.e. new liquid line lter drier(s) installed and all tubing
changes made - see Steps 4 and 5). The amount of time the compressor is open
to the atmosphere must be kept to a minimum.
Use the new mounting grommets and sleeves that are shipped with the
compressor to mount it. The sleeves will prevent over compression of the
grommets. Re-use the mounting bolts from the compressor that was removed. The
mounting bolts will bottom out when tight.
• Step 4. Install New Filter Driers (Select procedure that applies.)
IF the oil measured in Step 2 was not signicantly less than the amount shown in
the table above or the test for acid in Step 2 did NOT indicate burnout , install
a new R-410A refrigerant liquid line lter drier. The lter drier must be rated for
no less than 600 psig and be the proper size for the circuit. Because R-410A
refrigerant requires POE oil which absorbs moisture quickly, it is important to
change the lter drier any time the circuit is opened.
It is recommended to use a tubing cutter when cutting out a lter drier as the
desiccant absorbs and holds moisture better when it is cool. Heat from a torch
may cause moisture to leave the lter and be absorbed in the oil. Be careful to
keep dirt, lings, and other contaminants out of the system.
Continue to Step 5.
IF the oil measured in Step 2 was signicantly less than shown in the table above
or the test for acid in Step 2 did indicate compressor burnout, do the following:
a) Install a liquid line lter drier. If there is acid, install an acid removing lter
drier. Size the acid-removing lter drier at least one capacity size larger than
normally required for the circuit.
b) Install a temporary lter drier in the suction line. When there is acid, a 100%
activated alumina suction lter drier is recommended. The suction line drier
should be sized properly for the circuit and have a service access tting to
monitor pressure drop across the drier. (NOTE: Suction line lter drier must be
removed after 72 hours of operation.)
3.0 Maintenance/
Service
Procedures
(cont'd)
3.6 Compressor
Maintenance
(cont'd)
lower than listed in the table on page 14, clean the excess oil through use
of suction and liquid line lter driers. Beginning in Step 4, follow the same
procedure as for burnout cleanup.
Use an acid test kit to check the oil for acid. If acid is found, beginning in Step
Komentáře k této Příručce